After the first year of operation, ArcelorMittal Fos-sur-Mer leverages the benefits of BetaPlanner on its HSM - 25 Feb 2008

After the first year of operation, ArcelorMittal Fos-sur-Mer leverages the benefits of BetaPlanner on its HSM

Since October 2006, the HSM of ArcelorMittal Fos-sur-Mer is scheduled daily with the powerful and flexible AIS BetaPlanner mill scheduling solution.

 

The BetaPlanner has been configured to model all logistical and technological constraints of the mill and helps the schedulers with the complex and challenging task of mill scheduling.

 

An in-depth re-engineering of the rules of the Hot-Strip mill based on the physical model of the mill was performed. The scheduling team had to deal with a new set of constraints which gave more flexibility in the scheduling process, but increased the complexity of the manual scheduling. The main goal of the project was to give to the scheduler a tool that builds schedules according to the new set of rules in order to leverage the full flexibility of the new rules and to increase the size of the schedule.

 

Another major function of the system is the frequent update of the slabyard information (also with slabs arriving still hot from the casters).

 

"With the usage of BetaPlanner, we made Fos HSM Scheduling process enter into 21st century", says Mr. Basse, lead HSM scheduler in ArcelorMittal Fos-sur-Mer. "The BetaPlanner project helped us to achieve the following benefits

- Perfect and quick integration of the new rules
- High flexibility in case of unexpected drastic change (breakdown, new constraints, banned products, etc.)
- Easy tuning on the relative weights for due date respect, cost reduction, ...
- Appreciable increase of hot charging rate by checking every virtual slab
- Appreciable contribution to coffin size increase
- Time saving on Scheduling process allowing operators to dedicate on more value added tasks
"

 

The implementation also improves the transparency of the HSM production schedules and allows a clear and easy interpretation of rules for materials difficult to roll. In case of incidents on the mill (e.g. the downtime of one stand), the production constraints are better understood and taken into account in the scheduling process, avoiding production stoppage.

 

The BetaPlanner solution is also operating at several other sites of ArcelorMittal on Hot Strip Mills as well as on other lines such as cold mills, tandem pickling-cold mill lines, galvanising lines, dividing lines, and continuous annealing.

 

 

This release is also available at:

 

logoprzoom%2850%29.gif  PRZoom

logonewswire%2855%29.gif  NewsWireToday

 


back

To view this animation, you need the Adobe® Flash Player 8.
Unfortunately, this plugin was not found on your system. You can download and install the player from the Adobe® website.

© 2007 - Advanced information Systems
Wax Interactive
Sitemap | Privacy policy | Contact us